Maheswar Dam Work Suspended by Ministry of Environment and Forests |
|
On the second day of the hungerstrike by oustees of Maheshwar dam, the Ministry of Environment and Forests (MoEF) issued a letter ordering the immediate suspension of the construction of the Maheshwar Dam. Text of Letter Issued by MoEF 
Maheshwar dam if built will submerge fertile farm land and villages. "Negligible R&R work has been done" - MoEF
BY SPEED POST
No. J-11016/120/83-IAII
Government of India
Ministry of Environment and Forests
Paryavaran Bhawan
CGO Complex, Lodhi Road
New Delhi-110 003
Dated: 23.4.2010
Shri M.L. Gupta
Managing Director
Shree Maheshwar Hydel Power Corpn. Ltd.
801, 8th Floor, Ansal Bhawan
16, Kasturba Gandhi Marg
New Delhi-110001
Subject: Maheshwar Hydro Electric Project (10X40 MW) in Madhya Pradesh by Shree Maheshwar Hydel Power Corporation Ltd. – Non compliance of environmental conditions stipulated in the environment clearance letter dated 01.05.2001
Sir,
This has reference to the Show Cause Notice issued by the Ministry on 17th February, 2010 seeking clarification on the progress in implementation of Environmental Safeguard Measures and Rehabilitation and Resettlement and to explain why the environmental clearance should not be revoked and a direction for closer of the aforesaid project may not be issued.
2. The reply submitted by M/s Shree Maheshwar Hydel Power Corporation Ltd. Vide their letter dated 9th March, 2010 has been reviewed in the Ministry and found that the reply is not satisfactory on the following grounds:-
(i) Negligible R&R work has been done.
(ii) No agricultural land has been identified for rehabilitation purpose. Out of 22 submergence villages R&R is almost completed in respect of only Jalud village.
(iii) Two Wildlife Sanctuaries have not been created.
(iv) Backwater level calculation report of Central Water Commission which was supposed to be given in December 2009 has not yet been submitted.
3. The Central Government, therefore, in exercise of its power under Section 5 of the Environment (Protection) Act, 1986 hereby directs the project proponent to get the ongoing construction work at the Maheshwar Hydro Electric Project site suspended with immediate effect till a satisfactory compliance report on the above mentioned issues is submitted by the project proponent and the same is found to be implementable by this Ministry
4. The letter issues with the approval of the Competent Authority.
Your faithfully,
(Dr. S. Bhowmik)
Additional Director
Copy to:
1. Shri Avani Vaish
Chief Secretary
Government of Madhya Pradesh
Mantralaya, Vallabh Bhavan
Bhopal- 462 004
2. The Chairman
Madhya Pradesh Pollution Control Board
Paryavaran Parisar
E-5 Arera Colony
Bhopal-472 016
3. The Chief Conservator of Forests (Central)
Kendriya Paryavaran Bhavan
Link Road No. 3
Bhopal-472 016 |